Fuquay-Varina United Methodist Church · Fairway District, NC Conference
Building Project & Capital Campaign — Master Timeline
The full process on one timeline, from the Building Study Team through occupancy. Colored bars are the working teams; red diamonds are the required approval gates under the Book of Discipline, shown in their mandatory order. Planning estimate
Coordination (SST → Lead Team)
Building Study Team
Building Committee
Capital Campaign
Advisory Groups
Discipline gate
Building Study Team
Building Committee
Capital Campaign
Advisory Groups
Discipline gate
2026
2027
2028
2029
2030
Quarter
Q2
Q3
Q4
Q1
Q2
Q3
Q4
Q1
Q2
Q3
Q4
Q1
Q2
Q3
Q4
Q1
Q2
Q3
Q4
Phase
Study & discernment
Authorize & prelim design
Campaign & detailed design
Final approvals & financing
Construction & occupancy
The approval gates
1
Charge Conference charters the BST Aug 2026
District superintendent presides; commissions the study team.
District superintendent presides; commissions the study team.
2
Authorization gate ¶2544.2–.4 · Q3 2027
Pastor + DS written consent, District Board site approval, and the charge conference that authorizes the project and elects the Building Committee.
Pastor + DS written consent, District Board site approval, and the charge conference that authorizes the project and elects the Building Committee.
3
District Board preliminary approval ¶2544.6 · Q1 2028
Reviews statement of need, preliminary plans, cost, and financial plan.
Reviews statement of need, preliminary plans, cost, and financial plan.
4
Church Conference vote ¶2544.7 · Q2 2028
All professing members; simple majority approves the preliminary plan, cost, and financing. Formal pledge drive launches after this.
All professing members; simple majority approves the preliminary plan, cost, and financing. Formal pledge drive launches after this.
5
Final approval ¶2544.8 · Q1 2029
Charge conference and District Board approve detailed plans and a reliable cost estimate.
Charge conference and District Board approve detailed plans and a reliable cost estimate.
6
Debt authorization ¶2541 · Q2 2029
Two-thirds charge conference vote plus DS consent, if the church borrows. Compare BOMI (3% fixed), UM Foundation, and commercial lenders.
Two-thirds charge conference vote plus DS consent, if the church borrows. Compare BOMI (3% fixed), UM Foundation, and commercial lenders.
7
Construction begins ¶2544.9 · Q4 2029
Only after final approvals and once cash, pledges, and any loan commitment assure payment (¶2544.13). Groundbreaking.
Only after final approvals and once cash, pledges, and any loan commitment assure payment (¶2544.13). Groundbreaking.
8
Completion & dedication ~Q4 2030
Occupancy and first services; a larger scope may push this into 2031.
Occupancy and first services; a larger scope may push this into 2031.
Assumptions behind the dates
- The timeline is anchored to two fixed points you already have: the August 2026 charge conference that charters the BST, and the Trustees’ reverse-engineered earliest groundbreaking of late 2029 / early 2030. Everything between is spaced to honor the disciplinary order, not to compress it.
- The BST is the ¶2544.1 study committee. Its work and report come before the formal gates and feed the pastor + DS consent and the authorizing charge conference. It does not seek building approval itself.
- One Building Committee, elected at gate 2, develops preliminary then detailed plans, carries the project through the votes, and continues into construction with members added. The “study,” “planning,” and “execution” labels describe phases of one body’s life.
- The capital campaign is split: early conditioning and a feasibility study run during the study phase to test giving capacity and the congregation’s debt appetite; the formal pledge drive launches only after the church conference majority vote (gate 4), so people pledge toward an approved plan. Collection then continues for roughly three years.
- Gate 2 bundles three close-together requirements (pastor + DS consent, site approval, and the authorizing charge conference). A church may take these as one cluster or spread them across a quarter or two.
- The debt vote (gate 6) appears only if the church borrows. If FVUMC funds the project without a mortgage, that gate drops, though the gate-4 majority vote still stands.
- Construction is shown at roughly twelve months. The master-class guidance of a two-year minimum from “decide to build” to first service is comfortably respected here; the gates, not the building, set the pace.
Dates are planning estimates for SST and Building Study Team use, not commitments. The sequence of red gates is required by the Book of Discipline (¶2544, with debt under ¶2541); the spacing between them is the church’s to set. Prepared as a working master view to sit alongside the BST playbook.
